NEW DELHI: Under Bharatmala project, about 2,520 Km of roads amounting to Rs 44 thousandcrore have been envisaged in the State of Andhra Pradesh. Details of Bharatmala Roads is as under:

  1. Under Economic Corridor
  Length 

(in Km.)

Status
Madanapalli  –Pileru  Section of NH-71 54.86 DPR in progress
Pileru – Cherlopalli Section of NH-71 50.94 DPR in progress
Renigunta to Poyya section of NH-71 55.2 DPR in progress
Kadapa – Renigunta (NH-40) (Chennai – Puttur – Kadapa – Nandyal – Kurnool) 138 DPR in progress
AP / KN Border – Alur – Adoni section of Hasan – Raichur 83.89 DPR in progress
Visakhapatnam – Raipur Section:

Developmental works of NH-26 from Ondarangi –  Vizianagaramin  the state of Andhra Pradesh (Visakhapatnam – Raipur section).

70 DPR in progress
Sub Total 247.00  
B. Under Inter Corridor Routes    
Mydukur – Badvel section of NH – 67 41 DPR in progress
Badvel – Nellore 106.77 DPR in progress
Sub Total 147.77  
C. Under NHAI / NH (O)    
DPR for upgradation of the highway starting from junction with NH-44 at Anantapur – Giddalur of NH 544D in the State of Andhra Pradesh to Two / Four lane with paved shoulder configuration (Pkg-I & II) 139.00 DPR in progress
Two lane with paved shoulder of Anantapur – Giddalur of NH 544D (Pkg-III) (Bugga to Kaipa) 57.400 Bids Invited
Two lane with paved shoulder of Anantapur – Giddalur of NH 544D (Pkg-IV) (Kaipa to Giddalur) 77.569 Bids Invited
DPR for upgradation of the highway starting Giddalur to Guntur of NH 544D (Vinukonda – Guntur) in the State of Andhra Pradesh to Two / Four lane with paved shoulder configuration 83.00 DPR in progress
DPR for Upgradation of Kurnool – Dornala section of NH-340C to Two/Four lane with paved shoulder configuration 124.15 DPR in progress
Sub Total 481.119  
D. Ring Roads    
6-laning of Chilakaluripet Bypass on NH-16 under NHDP Phase-V on BOT(Toll) 16.384 DPR in progress
Feasibility Study Report for Construction of Outer Ring Road around Vijayawada – Guntur – Tenali Urban Agglomeration in the States of Andhra Pradesh on Green Field Alignment under NHDP Phase-VII 189 DPR in progress
Sub Total 205.384  
E Costal Roads    
Kathipudi – Ongole stretch of NH-216 (2l+PS/4L) 363 Work in progress in 9 packages
Sub Total 363  
F  Residual Works in NHDP    
Davulapally – Markapuram – Vagampalli – Dornala and Penchalkona – Yerpedu section of NH 565 (2L+PS) (Implemented in 4 packages) 287 Work completed
Mydukur – Nellore section of NH-67 (Implemented in 3 packages) (2L+PS) 149.5 Work completed
Ibrahimpatnam – Chandragudem and Chandragudem-A.P Telangana border section of NH 221 (Implemented in 2 packages) (2L+PS) 70.3 Work completed
Dornala – Penchalakona section of Nh-565 (2L+PS) 42 Work in progress
Karnataka/AP Border-Gooty section of NH-67 (4L) 57 Work in progress
Nagarjunsagar Dam- Davulpally section of NH-565 47 DPR complete
Davulpally reserve forest section of NH-565 22 DPR in progress
Sub Total 674.8  
G Connectivity of Backward districts and Religious and Tourist centres    
Malkangiri on NH 326-  Chintapalle-Naripattanam – Waddai – Chodavaram-Sabbavaram&Narsipatnam – Tuni section 280 DPR in progress
Route starting from NH-565 Gotlagattu – Podile – Uppalapadu – Chimakurti – Ongole on NH-16. 107 DPR in progress
Sub Total 387